Gore and Bagot Streets Sewer Separation
Project background
The Bagot and Gore Sewer separation is part of the ongoing attempt to separate storm and sanitary sewers and reduce sewer overflows to lake Ontario.
The project was designed and tendered in the fall of 2022 and awarded to Len Corcoran excavating.
Construction on Gore St. is between Ontario St. and King St E , Construction on Bagot St. is from Gore St to Earl St.
Construction began in May of 2023.
Project area
Design and Construction
Construction began on Gore St in May of 2023 at Ontario St. The installation of the new sanitary sewer will proceed to King St East . The crew will then move to Bagot St. in June of 2023 to complete a storm sewer installation.
Schedule and Project Downloads
Consruction is scheduled for May and June 2023.